Water storage project takes shape

Council’s Engineering Services team is managing the contract and overseeing construction and Council’s Water and Sewer team, including Water Treatment Plant Operators, have also provided valuable operational input throughout the design and construction process.
The Fort Bourke lookout access road will remain closed until roof installation has been completed to ensure public safety, with Council expecting to re-open the road in the coming weeks.
Once operational, the new reservoir will provide greater operational flexibility and strengthen the long-term reliability of Cobar’s water supply system, helping to meet the community’s future needs.

One of Cobar Shire Council’s biggest water infrastructure projects in recent years has reached a significant milestone, with the main structure of the new Fort Bourke Hill Water Reservoir now complete.

Construction on the new $4 million 5 megalitre reinforced concrete reservoir began earlier this year.

The project will improve the reliability, capacity and resilience of Cobar’s water supply network by providing additional treated water storage for the town and surrounding areas.

Council’s Director of Engineering Services Amer Tawfik reports the main concrete reservoir structure has now been completed, along with the installation of internal and external pipework, inlet and outlet pipeline connections, site civil works and fencing.

Mr Tawfik advises the work is on schedule.

“The next stage includes installation of the roof, access ladder and remaining electrical equipment, followed by commissioning and testing before the reservoir is placed into service.

“The project is expected to be completed within the next few weeks, subject to weather conditions and final commissioning activities,” Mr Tawfik said.

The project is being delivered by Cowra-based contractor Thompson Irrifab.

“The company has successfully delivered similar water infrastructure projects for several local government authorities, including Mid-Western Regional Council, Forbes Shire Council, Narromine Shire Council, and Hilltops Council.

A number of local businesses have also played an important role in the project.

“Additional excavation plant was supplied by Cynend Building & Construction to assist with the rock excavation works.

“Cobar Concrete supplied the concrete for the post-tensioned in-situ base slab, the infill concrete between the precast wall panels, the concrete pits and the service walkway surrounding the reservoir.

“Cobar Cranes provided the crane services required to install the post-tensioned precast concrete wall panels. In addition, the contractor has utilised local accommodation and catering services to support its workforce during construction,” Mr Tawfik reported.

“Wherever practical, the contractor has sought to engage local suppliers and service providers, helping to maximise the economic benefits

Council’s Engineering Services team is managing the contract and overseeing construction and Council’s Water and Sewer team, including Water Treatment Plant Operators, have also provided valuable operational input throughout the design and construction process.

The Fort Bourke lookout access road will remain closed until roof installation has been completed to ensure public safety, with Council expecting to re-open the road in the coming weeks.

Once operational, the new reservoir will provide greater operational flexibility and strengthen the long-term reliability of Cobar’s water supply system, helping to meet the community’s future needs.